目标时间因数 Tv 对应的固结时间 (EN 1997-1)
排水路径为 Hd、固结系数为 cv 的黏土层达到目标固结时间因数 Tv 所需的时间:t = (Tv · Hd²) / cv。
Catalog formula, not a design. Check input values, coefficients, and limits against the standard and its national annex.
Formula and quantities
| Symbol | Name | Unit | Note |
|---|---|---|---|
| 无量纲时间因数(例如 U = 90% 时取 0.848) | 1 | ||
| 最大排水路径长度 | m | ||
| 固结系数 | m²/s | ||
| 所需固结时间 | h | Result |
实例
= 0.848 1 · = 2 m · = 1e-6 m²/s
= 942.22 h
Standard and source
- Standard
- EN 1997-1:2004
- Result
- in h
Reference to clause and equation, no standard text. The description is written in our own words.