Distribution width bm of a concentrated point or line load at the top of the profiled steel sheeting according to EN 1994-1-1 Clause 9.4.3 Eq. (9.1): bm = bp + 2 · (hc + hf).

bm=bp+2⋅(hc+hf)\displaystyle b_{m} = b_{p} + 2 \cdot (h_{\mathrm{c}} + h_{f})
Apply in CALC

Catalog formula, not a design. Check input values, coefficients, and limits against the standard and its national annex.

hcbm

Formula and quantities

SymbolNameUnitNote
bp\displaystyle b_{p}Width of concentrated load perpendicular to spanmm
hc\displaystyle h_{\mathrm{c}}Thickness of concrete above ribsmm
hf\displaystyle h_{f}Thickness of floor finishesmm
bm\displaystyle b_{m}Load distribution width at sheeting topmmResult

Worked examples

Standard composite slab

bp\displaystyle b_{p} = 100 mm · hc\displaystyle h_{\mathrm{c}} = 80 mm · hf\displaystyle h_{f} = 50 mm

bm\displaystyle b_{m} = 360 mm

Heavy industrial slab

bp\displaystyle b_{p} = 200 mm · hc\displaystyle h_{\mathrm{c}} = 100 mm · hf\displaystyle h_{f} = 60 mm

bm\displaystyle b_{m} = 520 mm

Standard and source

Standard
EN 1994-1-1:2004, clause 9.4.3, Eq. (9.1)
Result
bm\displaystyle b_{m} in mm

Reference to clause and equation, no standard text. The description is written in our own words.

Try it

Unit system
bm\displaystyle b_{m} = 360 mm= (100 mm) + 2 · ((80 mm) + (50 mm))

Continue with Mia

Fills the input field in CALC; nothing is sent until you send it.

No matching formula yet? Find the right calculation rule.

Describe what you want to determine. Mia searches the formula catalog first and clarifies assumptions before anything is calculated.

The search starts in Design › Composite.

Miaknows the formula catalog and asks for what is missing.

You clarify missing information with Mia in the next step. Nothing is calculated yet.