地锚锚固段长度 Lbond

  • 类型:属性
  • 版本1
  • 2026/11/12已审核

地锚所需注浆体锚固长度:Lbond = Rak / (π · d · qsk)。

Lbond=Ra,kπ⋅d⋅qs,k\displaystyle L_\mathrm{bond} = \frac{R_{a,k}}{\pi \cdot d \cdot q_{s,k}}
Apply in CALC

Catalog formula, not a design. Check input values, coefficients, and limits against the standard and its national annex.

Ra,kLbonddqs,k

Formula and quantities

SymbolNameUnitNote
Ra,k\displaystyle R_{a,k}锚杆标准抗拔承载力kN
d\displaystyle d地锚注浆锚固体钻孔直径m
qs,k\displaystyle q_{s,k}注浆体与土层间的标准侧摩阻力N/m²
Lbond\displaystyle L_\mathrm{bond}所需锚固段长度mResult

实例

Ra,k\displaystyle R_{a,k} = 300 kN · d\displaystyle d = 0.15 m · qs,k\displaystyle q_{s,k} = 100,000 N/m²

Lbond\displaystyle L_\mathrm{bond} = 6.3662 m · Source: EN 1997-1:2004 条款 8.5.2

Scope and standard

符合EN 1997-1第8.5.2节的注浆地锚设计。

Standard
EN 1997-1:2004,第8.5.2条,式(8.2)
Result
Lbond\displaystyle L_\mathrm{bond} in m

Reference to clause and equation, no standard text. The description is written in our own words.

Try it

Unit system
Lbond\displaystyle L_\mathrm{bond} = 6.3662 m= (300 kN) / (pi · (0.15 m) · (100,000 N/m²))

Continue with Mia

Fills the input field in CALC; nothing is sent until you send it.

No matching formula yet? Find the right calculation rule.

Describe what you want to determine. Mia searches the formula catalog first and clarifies assumptions before anything is calculated.

检索将在 岩土工程 › 土压力 开始。

Miaknows the formula catalog and asks for what is missing.

You clarify missing information with Mia in the next step. Nothing is calculated yet.